North Carolina Data Center Electricity Taxed at 7% from August 2026: The Equipment Exemption Stays

North Carolina repealed the sales tax exemption for electricity used at certified datacenters: billing periods beginning on or after August 6, 2026 are taxed at 7%, and buyers file a separate report within 30 days after each quarter. The exemption for servers, cooling, UPS and other support equipment and software remains, subject to $75 million of investment over five years and ongoing wage and health insurance conditions.

Published By YCL CPA
Questions? Reach us directly

Message us on WhatsApp

Scan the code with WhatsApp, or tap the button if you are on your phone.

919-802-8376Open WhatsApp

Add us on WeChat

Scan the code with WeChat, or copy the WeChat ID and search for it in the app.

WeChat ID: YCLUSA
FacebookInstagramXRednoteWeChat Channels
North Carolina Data Center Electricity Taxed at 7% from August 2026: The Equipment Exemption Stays

North Carolina's 2026 budget law repealed the sales tax exemption for electricity used at datacenters. For billing periods beginning on or after August 6, 2026, electricity used at a certified datacenter is taxed at 7%, and the buyer must also file a quarterly report with the N.C. Department of Revenue. The exemption for servers, cooling, UPS systems and other datacenter support equipment and software is unchanged, and still requires certification by the N.C. Department of Commerce and at least $75 million of investment within five years.

For owners building datacenters in North Carolina, and for tenants leasing space and installing servers in certified facilities, power bills changed in the second half of 2026. Here is what the Department of Revenue's July 23, 2026 notice says and what to do about it.

What changed?

On July 7, 2026, the governor signed Senate Bill 257 (Session Law 2026-41), which repeals the electricity exemption for both datacenter categories: the qualifying datacenter and the eligible internet datacenter. House Bill 56 (Session Law 2026-42), signed the same day, set the effective date as the first billing period beginning at least 30 days after July 7, 2026, which means billing periods beginning on or after August 6, 2026.

Rate: electricity used at a datacenter is taxed at 7%, regardless of the county. A billing period that began before August 6 isn't taxed; every later billing period is.

Who does what: buyers that claimed the exemption must tell their electricity provider right away that they no longer qualify. Providers charge tax from the effective date, and buyers that don't pay owe the tax plus penalties and interest.

New quarterly report: buyers must report the sales tax paid on datacenter electricity within 30 days after each quarter, in an electronic format the Department prescribes. The first report was due October 30, 2026, covering the third quarter of 2026, and the Department said it would publish filing guidance beforehand.

Which exemptions remain?

The Department made clear that only the electricity exemption was repealed; the other datacenter exemptions are unchanged.

Support equipment at a qualifying datacenter: under G.S. 105-164.13(55a), datacenter support equipment used at a qualifying datacenter and capitalized for federal tax purposes is exempt. That includes server and computer hardware and software; power equipment such as UPS systems, batteries and power distribution units; cooling such as chillers, cooling towers, air handlers and pumps; and related computer research equipment.

Software used in a datacenter: software sold to a datacenter operator and used within the datacenter has its own exemption (G.S. 105-164.13(43a)).

Eligible internet datacenters: the separate exemption for large facilities used mainly for software publishing or internet activities, with $250 million of investment within five years in certain county tiers, also remains (G.S. 105-164.13(55)).

What counts as a qualifying datacenter?

Under G.S. 105-164.3, a datacenter must meet three conditions.

Investment: the N.C. Department of Commerce determines in writing that the owners, users and tenants together have invested or will invest at least $75 million in private funds within five years of the first investment. Only investments made on or after January 1, 2012 count.

Wages: it meets the wage standard for its county's development tier. Tier one counties have no wage standard; in tier two and three counties, the average weekly wage must be at least 110% of the lesser of the statewide average wage and 90% of the county average wage.

Health insurance: it provides health insurance to full-time employees, with the employer paying at least 50% of premiums.

Missed targets mean repayment: if the investment isn't made within five years, the exemption is forfeited and the tax comes due. A tenant buying equipment tax-free in a certified facility is in effect relying on the owner's and other tenants' investment progress.

What should owners and tenants do?

Owners: confirm the utility started charging tax with the right billing period, decide who files the quarterly report and with what data, and keep records of investment progress, wages and health coverage each year in case Commerce or Revenue asks.

Tenants: if the owner passes power costs through, the contract should say whether those charges include tax and who files the quarterly report. When buying equipment, give the exemption certificate the Department requires, and have the lease require the owner to maintain certification and say who pays if it lapses.

Budgets: power is one of a datacenter's largest operating costs, and 7% now goes straight on top. When comparing North Carolina with Virginia or Texas, include it in total cost. Virginia kept its equipment exemption in 2026 but added a tax of $0.011 per kWh on data center electricity from July 1, 2026 through June 30, 2028.

Example: what does a 2 MW suite pay?

Example (hypothetical numbers, to show the method): a cloud company leases about 2 MW in a certified North Carolina datacenter and draws 1.6 MW on average for 8,760 hours, or 14,016,000 kWh a year. At North Carolina's September 2026 average industrial price of 8.45 cents per kWh, the annual power bill is about $1,184,352.

The new sales tax is $1,184,352 x 7%, or about $82,905 a year. The same company's $30,000,000 of GPU servers used in the certified datacenter remain exempt; without the exemption, Wake County's 7.25% rate would mean $2,175,000. The equipment exemption is still worth far more than the new electricity tax costs, as long as certification holds.

What else to watch

Accounting: sales tax on electricity is generally part of the power cost and deductible currently. If the equipment exemption is later lost, the tax that comes due is generally added to the equipment's cost or expensed, depending on the facts.

Policy is still moving: several states are re-examining data center tax breaks. North Carolina kept the equipment exemption this time; check the latest General Assembly and Department of Revenue announcements for further changes.

For more, including server depreciation, import tariffs, SaaS sales tax and a North Carolina, California and New York comparison, see the data centers and cloud services guide. If you have a North Carolina datacenter project or lease, book a free 15-minute call or reach us on WeChat at YCLUSA.

Questions this article answers

When did North Carolina start taxing datacenter electricity?

For billing periods beginning on or after August 6, 2026. Session Law 2026-41 repealed the exemption, and Session Law 2026-42 made it effective for the first billing period beginning at least 30 days after the July 7, 2026 signing. Billing periods that began before August 6 aren't taxed.

What rate applies to datacenter electricity in North Carolina?

7%, regardless of the county. Buyers must also report the tax paid on datacenter electricity to the N.C. Department of Revenue within 30 days after each quarter, with the first report due October 30, 2026.

Are servers in a North Carolina datacenter still exempt from sales tax?

Yes. Only the electricity exemption was repealed. At a qualifying datacenter certified by the N.C. Department of Commerce ($75 million invested over five years, plus wage and health insurance conditions), server hardware and software, UPS and power distribution equipment and cooling systems remain exempt.

Can a tenant use the datacenter's certification to buy equipment tax-free?

Yes. The investment test counts owners, users and tenants together, and support equipment a tenant uses in a certified datacenter can be exempt with the required exemption certificate. If certification lapses or the five-year investment isn't met, the exemption can be clawed back, so the lease should allocate that risk.

Ready to talk? The first 15 minutes are on us.

Book online, or send us a few details and we will come back with a written quote within one business day.

Book a callQuick quote