The July 4, 2026 Solar Start Deadline Has Passed: New Projects Must Be in Service by End of 2027, Storage Isn't Affected

Solar and wind projects that began construction after July 4, 2026 must be placed in service by December 31, 2027 to claim 48E or 45Y; earlier starts generally get four years. Starts are shown only by the physical work test, with the 5% safe harbor left for small solar of 1.5 MWac or less. Storage keeps full credits through 2033 starts but must meet the material assistance ratio.

Published By YCL CPA
Questions? Reach us directly

Message us on WhatsApp

Scan the code with WhatsApp, or tap the button if you are on your phone.

919-802-8376Open WhatsApp

Add us on WeChat

Scan the code with WeChat, or copy the WeChat ID and search for it in the app.

WeChat ID: YCLUSA
FacebookInstagramXRednoteWeChat Channels
The July 4, 2026 Solar Start Deadline Has Passed: New Projects Must Be in Service by End of 2027, Storage Isn't Affected

Solar and wind projects that began construction after July 4, 2026 must be placed in service by December 31, 2027 to claim the 48E investment credit or the 45Y production credit. Projects that began construction by July 4, 2026 generally have four years to be placed in service. Storage isn't subject to this deadline and keeps the full credit for construction starts through 2033. As of November 2026 the start deadline has passed, so any new solar project has to be scheduled backward from an end-2027 in-service date.

Where does the deadline come from?

The One Big Beautiful Bill Act (P.L. 119-21), enacted July 4, 2025, rewrote how 48E and 45Y treat solar and wind. Solar and wind facilities that begin construction more than 12 months after enactment, meaning after July 4, 2026, must be placed in service by December 31, 2027. Facilities that began construction earlier aren't subject to the end-2027 cutoff; they follow the beginning-of-construction and continuity rules instead.

The same law kept the older, gradual phase-out for other technologies. Storage, geothermal and others get the full credit for construction starts through the end of 2033, 75% for 2034 starts and 50% for 2035 starts, and nothing after that. So within one solar-plus-storage project, the solar and the storage run on different clocks.

What counts as beginning construction?

On August 15, 2025 the IRS issued Notice 2025-42, which tightened the beginning-of-construction standard for solar and wind. For projects starting on or after September 2, 2025, the only way to show a start is the physical work test: physical work of a significant nature, such as on-site excavation, pile driving or pouring foundations, or off-site work on custom, non-inventory equipment for the project under a binding written contract (a specially designed transformer, for example). Buying off-the-shelf modules, doing design work or pulling permits doesn't count.

The familiar 5% cost safe harbor is essentially gone for solar and wind. It survives only for small solar facilities of 1.5 MWac or less.

Once construction starts, work has to continue. Notice 2025-42 keeps the continuity safe harbor: a project placed in service within four calendar years after the year construction began is treated as meeting the continuity requirement. A project that began construction in May 2026, for example, generally has until the end of 2030.

How should you schedule a solar project that starts after July 4, 2026?

These projects have one hard deadline: placed in service by December 31, 2027. Placed in service generally means the system is installed and tested, has the permits and interconnection approval it needs, and is ready to produce power for its intended use. A system that's built but still waiting on interconnection approval may not qualify yet.

In practice you work backward from that date: equipment delivery (which tariffs and trade cases can delay), building and electrical permits, utility interconnection review and final inspection. Commercial rooftop projects usually take a few months; ground-mounted plants and projects that need grid upgrades can take more than a year. When you sign the construction contract, it's worth making the end-2027 in-service date a key term and spelling out who bears the cost of a delay.

What about the storage portion?

The 48E credit for storage isn't subject to the end-2027 cutoff, but two points matter.

Track costs separately. Solar and storage costs need to be accumulated separately. If the solar misses its in-service deadline, only the solar credit is lost; the storage credit is still available. Shared inverters, transformers and engineering costs have to be allocated on a reasonable basis.

The foreign entity rules are tougher. Projects that begin construction in 2026 or later must compute a material assistance cost ratio: the share of direct costs not sourced from prohibited foreign entities. Solar facilities need 40% for 2026 starts and storage needs 55%, with both rising 5 points a year (storage tops out at 75%). Chinese battery cells are a large share of storage cost, so this is where storage projects most often run into trouble. Treasury issued interim guidance in Notice 2026-15 on February 12, 2026.

What is the credit rate?

The 48E base rate is 6%. It's multiplied by five, to 30%, if the project meets the prevailing wage and apprenticeship (PWA) requirements or is under 1 MWac. Domestic content and energy community bonuses can add up to 10 points each, and small projects in low-income communities can apply for a separate allocation. For projects of 1 MWac or more, keep weekly payroll records during construction; you'll need them for the claim and for any transfer.

Credits you can't use can be sold

If you can't use the credit yourself, §6418 lets you sell it once, for cash, to an unrelated buyer. Before selling, complete IRS pre-filing registration through Energy Credits Online to get a registration number for each project, then attach Form 3800 and the transfer election to your timely filed return for that year. The seller doesn't include the cash in income, and the buyer can't deduct what it pays. The new law bars sales to specified foreign entities.

If 48E property is disposed of or changes use within five years after it's placed in service, the credit is recaptured, and after a transfer the recapture falls on the buyer. That's why buyers ask for indemnities and complete cost, start-of-construction and placed-in-service records.

Example: one project, two outcomes

Example (hypothetical numbers, to show the method): a North Carolina company owned by U.S. persons signs a contract in September 2026 to put 500 kWac of solar and 1 MWh of storage on its warehouse roof. Eligible solar cost is $900,000 and storage $500,000. The project is under 1 MWac, so the credit rate is 30%.

If it's placed in service in June 2027: $270,000 for the solar plus $150,000 for the storage, $420,000 in total.

If interconnection approval drags and the system isn't placed in service until February 2028: the solar began construction after July 4, 2026 and missed the end-2027 deadline, so the $270,000 is lost. The storage credit is unaffected and remains $150,000, as long as the material assistance ratio is met.

Either way, depreciable basis is reduced by 50% of the credit claimed. 48E property is 5-year MACRS property, and property acquired after January 19, 2025 can take 100% bonus depreciation. North Carolina doesn't follow federal bonus depreciation, so the state return needs its own calculation.

Next steps

For tariffs, the foreign entity rules, and licensing and sales tax in North Carolina, California and New York, see the solar and energy storage guide. If the project isn't signed yet, work out the in-service deadline, the material assistance ratio and whether PWA applies first. Book a free 15-minute call or add WeChat YCLUSA.

Sources

P.L. 119-21 (One Big Beautiful Bill Act), July 4, 2025

IRS Notice 2025-42, Beginning of construction for wind and solar facilities

IRS Notice 2026-15, Material assistance from prohibited foreign entities

IRS IR-2026-23: Guidance on material assistance by prohibited foreign entities (Feb. 12, 2026)

IRS: Elective pay and transferability

26 U.S. Code §6418

IRS: Instructions for Form 3468

Last checked: November 25, 2026

This article is general tax information, not tax, legal or customs advice for any individual situation. These rules change quickly; the latest IRS, Treasury, CBP and Commerce guidance controls, and results depend on the facts.

Questions this article answers

Can a solar project that began construction after July 4, 2026 still get 48E?

Yes, if it's placed in service by December 31, 2027. That's the deadline the 2025 law set for solar and wind; a solar facility that misses it can't claim 48E or 45Y. Storage isn't subject to this deadline.

How do you show a solar project began construction by July 4, 2026?

Under IRS Notice 2025-42, solar and wind projects starting on or after September 2, 2025 can use only the physical work test, such as on-site excavation or pile driving, or off-site work on custom, non-inventory equipment under a binding contract. The 5% cost safe harbor remains only for small solar facilities of 1.5 MWac or less.

If construction began before July 4, 2026, when must the project be in service?

Generally the four-year continuity safe harbor applies: a project placed in service within four calendar years after the year construction began meets the continuity requirement. A project that began in May 2026, for example, generally has until the end of 2030.

In a solar-plus-storage project, does a late solar in-service date hurt the storage credit?

No. The 48E credit for storage isn't subject to the end-2027 deadline and stays at full value for construction starts through 2033. Track solar and storage costs separately and allocate shared costs reasonably; storage also needs a 55% material assistance cost ratio for 2026 starts.

What if we can't use the credit ourselves?

Under §6418 you can sell it once, for cash, to an unrelated buyer. Register first through the IRS Energy Credits Online portal for a registration number, then make the transfer election on a timely filed return. The cash isn't taxable to the seller, and sales to specified foreign entities aren't allowed.

Ready to talk? The first 15 minutes are on us.

Book online, or send us a few details and we will come back with a written quote within one business day.

Book a callQuick quote