How construction contractors recognize revenue: percentage of completion, completed contract and the 2026 $32 million small contractor exception
For tax, long-term construction contracts default to the §460 percentage-of-completion method, which follows costs, not collections. Contracts expected to finish within two years by contractors averaging $32 million or less in receipts (2026) are excepted, and the 2025 law extended the residential exception to apartments and condos. When retainage is income, how to file Form 3115, and a worked example.

For tax purposes, long-term construction contracts default to the §460 percentage-of-completion method (PCM): you recognize revenue each year based on costs incurred over estimated total costs, regardless of billings or collections. Two exceptions allow the completed-contract method (CCM) or other methods. The first is residential construction contracts, which since the 2025 law include apartments and condominiums. The second is other contracts expected to finish within two years, signed by a contractor whose average gross receipts for the prior three years don't exceed $32 million (2026). Which method you use decides which year your profit is taxed.
Why is contractor revenue different from other businesses?
A commercial upfit or a building often spans two or three tax years. You bill by progress, the owner holds back retainage, and costs come before cash. The tax question is simple to state: on a job that crosses years, which year does the profit belong to?
Section 460 says long-term contracts (building, construction or installation contracts not completed in the tax year they're entered into) generally use percentage of completion. Small contractors and residential work have exceptions, and those exceptions are the focus here.
How does percentage of completion work?
The usual approach is cost-to-cost: cumulative revenue recognized equals the contract price times cumulative costs incurred divided by estimated total costs, minus revenue recognized in earlier years. You update the estimate every year, and changes flow into later years' revenue.
Billings and collections don't matter. Amounts billed ahead of costs aren't revenue yet, and costs incurred but not yet billed still produce revenue.
After the job is finished, you run the look-back calculation: recompute each year's revenue using actual total costs, compare it with the tax paid on the estimates, and settle the difference as interest on Form 8697. Small contracts (price no more than the lesser of $1 million or 1% of average gross receipts, completed within two years) are exempt from look-back.
The small contractor exception: both tests must be met
First, gross receipts. In the year you sign the contract, your average annual gross receipts for the prior three tax years under §448(c) must not exceed the threshold: $31,000,000 for 2025 and $32,000,000 for 2026 (Rev. Proc. 2025-32). Receipts of commonly controlled and related companies are added together. Individuals and single-member LLCs apply the test business by business. Tax shelters can't use the exception.
Second, duration. When you sign, you expect to finish within two years of the start date. This is a reasonable estimate at signing; an owner's change orders that later stretch the schedule generally don't undo it, but the estimate should be supported, for example by a project schedule.
Contracts that pass both tests don't have to use PCM. You can use the completed-contract method, accrual billings or another permitted method, and a company under the threshold can generally use the cash method too.
The 2025 law widened the residential exception
Before the change, only home construction contracts were exempt from PCM regardless of company size: contracts where 80% or more of estimated costs went to dwelling units in buildings with four or fewer units, plus related on-site improvements. Apartment and condo contracts that didn't meet the small contractor tests used PCM or a hybrid rule (70% PCM, 30% another method).
Section 70430 of P.L. 119-21, signed July 4, 2025, replaced home construction contracts with residential construction contracts and dropped the four-unit limit. Any contract where 80% or more of estimated costs go to dwelling units (however many units the building has) and related on-site improvements can skip PCM. The rule applies to contracts entered into in tax years beginning after July 4, 2025; for a calendar-year company, that means contracts signed from January 1, 2026.
Two cautions. Large residential contractors that don't meet the small contractor tests still capitalize costs under §263A, and for residential contracts that aren't home construction contracts the duration test for that purpose is three years. And method changes have to follow procedure; the IRS issued Rev. Proc. 2026-32 in September 2026 with automatic change procedures for these contracts.
When is retainage income?
Retainage is the part of each progress payment the owner holds until the job is accepted, and GCs hold it from their subs too. North Carolina public projects and California and New York private contracts now cap it at 5%.
The tax timing depends on your method. Under percentage of completion, revenue follows costs and retainage doesn't change anything. Under the accrual method without CCM, the IRS position (Rev. Rul. 69-314) is that retainage is generally income when the right to it becomes fixed, which usually means after acceptance. Under the cash method, it's income when received.
The same logic runs the other way: retainage a GC holds from its subs generally isn't deductible until the liability is fixed. Keep retainage receivable and retainage payable as separate accounts, tracked by job.
Example: one job, two methods
Example (hypothetical numbers, to show the method): a North Carolina GC with $6 million of average gross receipts over the prior three years signs a commercial upfit in August 2026 for a fixed price of $1,200,000, with estimated total cost of $1,000,000 and expected completion in May 2027. By year-end 2026 it has incurred $450,000 of costs and billed $600,000; the owner held $30,000 of retainage, so it collected $570,000.
Percentage of completion: percentage complete is $450,000 ÷ $1,000,000 = 45%. Revenue for 2026 is $1,200,000 × 45% = $540,000, and gross profit is $90,000. The rest comes in 2027, followed by the look-back calculation.
Completed contract: $6 million of average receipts is under $32 million and the job should finish within two years, so CCM is available. Nothing is recognized in 2026, not even the $570,000 collected; about $200,000 of gross profit is recognized when the job is completed in 2027.
Total profit is the same either way; only the year changes. CCM pushes the $90,000 from 2026 into 2027, but if other large jobs also finish in 2027, income bunches into one year and may be taxed at a higher rate. For an S corporation, profit is taxed to the owners and should be planned together with their salaries.
How do you change methods?
Moving off PCM generally takes a Form 3115 accounting method change. A change under the small contractor exception uses the cut-off method: it applies only to contracts entered into in the year of change and later, jobs in progress stay on the old method, and there's no §481(a) adjustment.
Once your receipts cross $32 million, new contracts go back to PCM. If you're growing fast, project receipts a few years ahead so you know when PCM will apply again.
Why are there two sets of numbers?
The financial statements your bank and surety want follow GAAP (ASC 606), which recognizes most construction revenue over time as you perform, close to PCM. If your tax return uses CCM or the cash method, book and tax profit differ and you need a reconciliation. Sureties also look at overbillings and underbillings on the WIP schedule, and those have to tie to the books.
Next steps
For licensing, sales tax on materials, labor and equipment depreciation, see the full construction contractors guide. To check whether your company qualifies for the small contractor exception and whether switching methods pays off, book a free 15-minute call or message us on WeChat at YCLUSA.
Sources
IRS Rev. Proc. 2025-32 (2026 inflation adjustments, §448(c) threshold)
Last checked: November 25, 2026
This article is general tax information, not tax or legal advice for any individual situation. The latest IRS guidance controls, and results depend on the facts.
Questions this article answers
What is the small contractor gross receipts threshold for 2026?
Under Rev. Proc. 2025-32, for tax years beginning in 2026 the §448(c) threshold is average annual gross receipts of $32,000,000 or less for the prior three years ($31,000,000 for 2025). Related companies are aggregated. The contract must also be expected, when signed, to finish within two years; only contracts meeting both tests can skip the percentage-of-completion method.
Can a general contractor building apartments now use the completed-contract method?
Yes. P.L. 119-21 widened the exception from home construction contracts (four or fewer units) to all residential construction contracts, meaning contracts where 80% or more of estimated costs go to dwelling units and related on-site improvements. It applies to contracts entered into in tax years beginning after July 4, 2025. Large contractors that don't meet the small contractor tests still capitalize costs under §263A.
When is retainage held by the owner taxable?
It depends on the method. Under percentage of completion, revenue follows costs, so retainage doesn't change the timing. Under the accrual method, the IRS position is that retainage is generally income when the right to it becomes fixed, usually when the job is accepted. Under the cash method, it's income when received.
What does it take to switch from percentage of completion to completed contract?
Generally a Form 3115 accounting method change. A change under the small contractor exception applies on a cut-off basis to contracts entered into in the year of change and later, so jobs already underway stay on the old method. Rev. Proc. 2026-32 provides automatic change procedures for residential construction contracts.